Quick answer

A 20 x 20 ft grid of #4 bar at 16 in on centre needs 30 bars 585 linear feet including 0 lap splices, which is 30 sticks of 20 ft bar weighing 391 lb ($371).

Disclosure: CementCalc is free to use and supported by ads and affiliate links. As an Amazon Associate we earn from qualifying purchases. Full disclosure.

Slab and grid

16–18 in residential

3 in against soil

20 ft is standard; 10 ft at big-box stores

40d rule of thumb

bars = floor(clear span / spacing) + 1  |  lap = 40 x bar ⌀ = 20 in  |  weight = length x lb/ft

Steel takeoff

20 ft sticks to buy

30

585 linear ft including splices

Bars each way

15 x 15

Cut to 19.5 ft and 19.5 ft

Weight

391lb

0.2 tons

Steel cost

$371

Tie intersections

225

Tie the perimeter and alternate inside

Mesh alternative

The same 400 sq ft would take about 9 sheets of 5 x 10 ft welded wire mesh with 10% overlap. Mesh is cheaper and faster for crack control on a 4 inch slab, but it carries far less load than a bar mat.

Published figure — source: Bar geometry derived from the eighths-of-an-inch designation and steel density 0.2836 lb/in³

Bar sizes, weights and areas

BarMetricDiameterAreaWeight40d lapTypical use
#3No. 100.375 in0.11 in²0.376 lb/ft15 inSlabs on grade, sidewalks, small footings
#4No. 130.5 in0.196 in²0.668 lb/ft20 inDriveways, patios, residential footings
#5No. 160.625 in0.307 in²1.044 lb/ft25 inFoundation walls, heavier slabs, piers
#6No. 190.75 in0.442 in²1.503 lb/ft30 inStructural footings, grade beams
#7No. 220.875 in0.601 in²2.046 lb/ft35 inColumns and beams
#8No. 251 in0.785 in²2.673 lb/ft40 inColumns, heavy beams
#9No. 291.125 in0.994 in²3.383 lb/ft45 inHeavy structural work
#10No. 321.25 in1.227 in²4.176 lb/ft50 inHeavy structural work
#11No. 361.375 in1.485 in²5.053 lb/ft55 inHeavy structural work
Derived from the bar designation (diameter in eighths of an inch) and the density of steel.

Steel only works where it sits. Rebar laid on the subgrade and pulled up "as you pour" ends up at the bottom of the slab where it does nothing for the tension face — set it on chairs at mid-depth, or in the upper third for a slab on grade in tension from above.

Bar length here is the clear span after cover is deducted from both ends, so add nothing extra for cover. Splices are added automatically whenever a run exceeds your stock length.

Source & method: Bar diameter comes from the US designation (bar number / 8 inches), area from pi x d²/4, and weight per foot from area x 12 in x 0.2836 lb/in³, the density of steel. This reproduces published nominal weights without copying a specification table.

Reinforcement supplies

Links below are affiliate links. If you buy through them we may earn a commission at no extra cost to you.

Frequently asked questions

How much rebar do I need for a concrete slab?
Count bars in each direction as (clear span / spacing) + 1. A 20 x 20 ft slab with #4 bar at 16 inches on centre and 3 inches of cover takes 16 bars each way — about 620 linear feet, or 31 twenty-foot sticks, weighing roughly 415 lb.
What size rebar for a 4 inch slab?
#3 or #4 bar at 16 to 18 inches on centre, or welded wire mesh, is typical for a residential 4 inch slab. Driveways and vehicle areas usually get #4 at 16 inches. Structural slabs are engineered — follow the drawings.
How far apart should rebar be in a slab?
16 to 18 inches on centre each way is the common residential grid, tightened to 12 inches for heavier loads. Keep 3 inches of cover from soil-facing faces and edges, and support the steel at mid-depth on chairs.
How much does rebar weigh per foot?
#3 is 0.376 lb/ft, #4 is 0.668 lb/ft, #5 is 1.043 lb/ft and #6 is 1.502 lb/ft. Bar number is the diameter in eighths of an inch, so weight follows the square of the number.
How long should a rebar lap splice be?
A common rule of thumb for non-structural residential slabs is 40 bar diameters — about 20 inches for #4 bar. Structural work uses code-specified development lengths that depend on concrete strength, bar coating and cover, so follow the engineer's drawings.