Quick answer

A 20 x 20 ft slab at 4 in thick needs 5.5 yd³ of concrete. Ready-mix delivered comes to $1,028, while 245 bags of 80 lb mix cost $1,838 ready-mix saves $810. Concrete alone works out to $3 per sq ft.

Disclosure: CementCalc is free to use and supported by ads and affiliate links. As an Amazon Associate we earn from qualifying purchases. Full disclosure.

Slab

Ready-mix pricing

Bagged mix pricing

40, 50, 60 or 80

Base, steel and labor

Mesh ≈ $0.35, #4 grid ≈ $0.85

Set to 0 for a DIY pour

ready-mix = yards x $/yd³ + delivery + max(0, minimum − yards) x short-load fee

Cost summary

Concrete delivered

$1,028

5.5 yd³ + $120 delivery

Bagged alternative

$1,838

245 x 80 lb bags

Materials total

$1,744

Concrete + base gravel + reinforcement

Installed total

$3,344

$8 per sq ft

Line items

ItemQuantityCost
Concrete5.5 yd³$908
Delivery1 truck$120
Short-load fee0 yd³ short$0
Base gravel9.9 tons$376
Reinforcement400 sq ft$340
Labor400 sq ft$1,600
Estimates for planning. Get a live quote from your local ready-mix plant before you order.

Slab volume 4.94 yd³ before waste, 5.43 yd³ with 10% waste, 11 tons placed.

What actually drives slab cost

Concrete itself is rarely the biggest line. On a typical residential slab the mix is 25 to 35 percent of the installed price; forming, base preparation, reinforcement and finishing labor make up the rest. That is why a 20 x 20 ft slab does not cost twice a 10 x 20 ft slab — the fixed costs of a truck, forms and a crew spread across more area.

Watch the truck minimum. A 1.5 yard order on a 4 yard minimum can carry more in short-load fees than the concrete costs, which is the one case where mixing bags on site genuinely wins.

Thickness is linear in cost, so specify what the use needs: 4 inches for foot traffic, 5 to 6 where a vehicle parks. Skipping base gravel to save money is the false economy — the slab cracks where the subgrade settles, and that repair costs more than the stone would have.

Source & method: Cost model computed in your browser from the volume geometry plus the unit prices you enter. Default prices are typical US ranges as of 2026 and are editable — nothing is fetched from a paid database.

Base prep gear

Links below are affiliate links. If you buy through them we may earn a commission at no extra cost to you.

Forming supplies

Links below are affiliate links. If you buy through them we may earn a commission at no extra cost to you.

Frequently asked questions

How much does a concrete slab cost?
Material alone runs about $140 to $190 per cubic yard of ready-mix delivered, which is roughly $2 to $3 per square foot at 4 inches thick. A finished slab installed by a contractor typically costs $6 to $12 per square foot because labor, forming, base gravel and reinforcement are the larger share.
Is it cheaper to pour concrete yourself or buy bags?
Bags are cheaper below about half a cubic yard and much more expensive above one yard: 80 lb bags work out near $340 per cubic yard of finished concrete at $7.50 a bag, against $165 for ready-mix. Bags win only when the pour is too small to justify a truck.
What is a short-load fee?
Ready-mix plants charge a per-yard penalty when your order is under the truck minimum, commonly 3 to 5 yards. The fee is often $30 to $60 for every yard short, so a 2-yard order on a 4-yard minimum can add $60 to $120.
Does a thicker slab cost much more?
Cost scales directly with thickness: going from 4 to 6 inches is 50 percent more concrete. On a 400 sq ft slab that is about 2.5 extra cubic yards, so roughly $400 more in material.